Must read

Families refusing access to support
SPONSORED

Unlocking legal talent

How hair strand testing should be instructed for family court proceedings
Webinars

Allocating risk in amended JCT contracts: Lessons from John Sisk & Son Limited v Capital & Centric (Rose) Limited
David Owens and Elizabeth Withers explore recent developments in construction contract case law.
- Details
In this article, we build upon the insights shared in our previous article, which outlined key considerations when negotiating standard form construction contracts, discussing lessons learnt from a recent case from the Technology and Construction Court (TCC) involving electronic and hard copy versions of the same document:
John Sisk and Son Limited and Capital & Centric (C&C)(Rose) Limited [2025] EWHC 594
Background to the dispute:
This case involved a JCT D&B 2016 contract for the design and construction of substantial works at Weir Mill, Chestergate, which contained substantial amendments.
A dispute arose as to who is contractually responsible for the risks associated with the ground conditions and the existing structures on the site, including their ability to support and/or facilitate the proposed works.
Prior to the proceedings, there had been an adjudication whereby the adjudicator found in C&C’s favour, concluding that “…the responsibility for ground conditions including the identification of the basements, structures, voids, compressed structural elements and obstructions under the existing West Mill was solely Sisk’s risk”.
As a result, this risk meant that Sisk was unable to claim an extension of time and/or any additional costs it incurred.
In a Part 8 claim, HHJ Stephen Davies held that on a proper interpretation of an amended JCT DB 2016, the risk of the unsuitability of existing structures was an employer risk. In doing so, the judge reached the opposite conclusion from the adjudicator.
Key contractual provisions and their interpretation
The dispute hinged on the interpretation of clauses 2.42.1 to 2.42.4 of the amended JCT contract and the relationship between those provisions and documents referred to as “Clarifications” in the Employer’s Requirements.
Clauses 2.42.1 – 2.42.3: Contractor risk
- Clause 2.42.1 provided that C&C gave no warranty or representation as to the condition of the site or the accuracy of any survey data provided;
- Under Clause 2.42.2, Sisk was deemed to have fully inspected and accepted the site conditions and the existing structures, without entitlement to additional payment or extension of time for any misunderstanding; and
- Clause 2.42.3 required Sisk to take sole responsibility for ensuring the suitability of the site and existing structures for the intended works, with no entitlement to extra payment or time for related risks.
Clause 2.42.4: A limited carve-out
- Clause 2.42.4 stated that the above provisions were “subject to item 2 of the Clarifications”.
- The term “Clarifications” was defined to refer to the “Contract Clarifications” included within the Employer’s Requirements.
- Item 2 of that document expressly stated that C&C bore the risk relating to the suitability of the existing buildings.
Conflicting documentation
An issue then arose due to the existence of two documents:
- The Contract Clarifications, which were included in the printed contract stated that the employer took on the existing structures risk; and
- The Tender Submission Clarifications, which was not included in the printed version of the contract but was present in the electronic version. This earlier document recorded a disagreement between the parties about risk allocation and noted the employer’s rejection of the contractor’s request for a carve-out.
C&C argued that the Tender Submission Clarifications formed part of the contract documents and supported the adjudicator’s conclusion. However, the judge disagreed.
The court’s findings
The court held that:
- The qualification in clause 2.42.4 applied only to the Contract Clarifications.
- The term “Employer Risk” in that document had a clear and unambiguous meaning, creating a limited carve-out to the otherwise wide contractor obligations in clause 2.42.
- The Tender Submission Clarifications were not part of the contract. They were not referenced in the contract documents schedule, nor was there any indication they were included in the contract by reference or by signature.
Key takeaways
As discussed in our previous article, when negotiating construction contracts, clarity and consistency remain important considerations, as well as the fact that parties cannot rely on negotiation history where this is not reflected in a proper interpretation of the contract. Building upon this consideration, the following takeaways are key in light on the Sisk v C&C case:
- Be wary of conflicting documentation
- Ensure that all documents forming part of the contract are clearly identified and consistent.
- Avoid relying on different versions of documents (electronic vs. printed) unless explicitly agreed.
- Confirm documentation in the contract: Always confirm what documentation is included and referenced in the executed agreement to prevent issues arising from different formats (electronic or printed).
Conclusion
The Sisk v C&C decision is a reminder for parties involved in construction projects of the importance of clarity and consistency in contract drafting. Where standard forms are amended, those amendments must be precise, and the inclusion of additional documents must be managed with care.
David Owens is a Partner and Elizabeth Withers is a Trainee Solicitor at Sharpe Pritchard LLP.
For further insight and resources on local government legal issues from Sharpe Pritchard, please visit the SharpeEdge page by clicking on the banner below.
This article is for general awareness only and does not constitute legal or professional advice. The law may have changed since this page was first published. If you would like further advice and assistance in relation to any issue raised in this article, please contact us by telephone or email enquiries@sharpepritchard.co.uk.
Click here to view our archived articles or search below.
|
OUR RECENT ARTICLES IPA guidance 2025: Managing PFI distress and preparing for expiry
Jul 03, 2025
Aanya Gujral and David Owens dive into the recent guidance published on managing the risks associated with Private Finance Initiative (“PFI”) projects.
Data (Use and Access) Act – Updating Data Protection Law and more
Jul 03, 2025
On the 19th June 2025, the Data Use and Access Bill (“DUA Bill”) received Royal Assent to become the Data Use and Access Act 2025 (“DUA Act”).
Modifying subsidies: What is permitted and what is not?
Jun 24, 2025
Beatrice Wood and Oliver Slater explore recent developments and discuss the process of awarding subsidies.
Getting new PPP right: Smarter tools for smarter infrastructure
Jun 24, 2025
Nicola Sumner, Steve Gummer and Roseanne Serrelli discuss the 'dos and don'ts' of Public-private Partnerships in their new form.
Zones/RABs and heat networks: The path to an investible infrastructure asset class?
Jun 19, 2025
The UK’s new heat network zoning framework (the outlines for which were drawn by the Energy Act 2023) is set to redefine how low‑carbon heating is delivered by creating geographic zones, where district heat networks are the mandated, optimal solution.
Partial debt guarantees- Reviving Investment in UK Water Infrastructure
Jun 17, 2025
Is it Time for a Public Sector Major Infrastructure Debt Guarantor?
Court gives clarity on consultations : R (The National Council for Civil Liberties) and others v The Secretary of State for the Home Department
Jun 10, 2025
Chloe Woodward and Joe Walker discuss a recent judgment on when engagement with third parties constitute a formal consultation and must therefore adhere to case law on being 'run fairly'.
URS Corporation Limited v BDW Trading Limited [2025] UKSC 21 – Supreme Court hands down significant judgment for the construction industry
May 27, 2025
Helen Arthur explores a recent Supreme Court judgment on building safety in high-rise buildings, explaining what the decision means for defects claims.
Catch me if you can: Local government blazes a trail in increased SME spending
May 21, 2025
Juli Lau and Natasha Barlow take readers through the report published by the BCC on procurement spending.
Lessons in public consultation: High Court finds failures in local authority’s consideration of consultation responses
May 21, 2025
George McLellan and Samuel Hart explore the High Court decision ruling that Lambeth Council broke the law in the process of establishing an LTN in the borough.
Allocating risk in amended JCT contracts: Lessons from John Sisk & Son Limited v Capital & Centric (Rose) Limited
May 12, 2025
David Owens and Elizabeth Withers explore recent developments in construction contract case law.
Election challenges
May 01, 2025
Emyr Thomas dives into the details of how election results can be challenged and what those who wish to challenge a result can expect.
|
ABOUT SHARPE PRITCHARD We are a national firm of public law specialists, serving local authorities, other public sector organisations and registered social landlords, as well as commercial clients and the third sector. Our team advises on a wide range of public law matters, spanning electoral law, procurement, construction, infrastructure, data protection and information law, planning and dispute resolution, to name a few key specialisms. All public sector organisations have a route to instruct us through the various frameworks we are appointed to. To find out more about our services, please click here. |
OUR NEXT EVENT
|
OTHER UPCOMING EVENTS
![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() |
20-08-2025 10:00 am
15-09-2025 10:00 am
08-10-2025 10:00 am
18-07-2025 9:30 am
10-09-2025 11:00 am