- Details
No overlap between substance and jurisdictional issues
Clare Mendelle and James Goldthorpe examine the implications of Ex Novo Limited v MPS Housing Limited [2020] EWHC 3804 (TCC)]
Case Background
In this case Ex Novo sought to enforce an adjudicator’s decision in its favour. MPS Housing, resisting enforcement, argued that the adjudicator did not have jurisdiction because the adjudication reference related to multiple contracts and an adjudicator does not (without the parties’ agreement) have jurisdiction to determine disputes under multiple contracts. The adjudicator had addressed the single vs multiple contracts issue and determined that the allegedly separate contracts were in fact a single contract that was subsequently varied.
Questions for the Judge
The two questions for the TCC judge were:
- Whether the adjudicator had jurisdiction. This turned on whether there was a single contract with multiple instructions or multiple contracts.
- Whether the adjudicator’s decision that there was a single contract was a decision he had jurisdiction to make. If it was, then the decision would be enforceable even if incorrect.
Reasoning
After considering the authorities, the judge determined that the proper approach to take would depend on whether the reference to the adjudicator necessarily involved the adjudicator having jurisdiction to determine jurisdiction. In other words, if that decision was an integral part of the substantive reference then the decision was unchallengeable. However, if that decision was only a preliminary matter to be decided before determining the reference proper, then the decision was challengeable. As such, the court needed to look at all of the circumstances and decide whether the reference entitled the adjudicator to determine jurisdiction as part of the substantive reference, or whether it was a necessary preliminary matter.
Decision
While the adjudicator did have to decide whether there was a single contract or multiple contracts, he did not have to answer that question in order to make a decision on the substantive issue between the parties, which was regarding payment and the effect of the absence of a pay less notice from MPS Housing. Rather, he had to answer the question for the purpose of deciding whether he had jurisdiction and should proceed with the adjudication. As such the decision was a preliminary matter and, therefore, non-binding and potentially challengeable.
The judge then considered the single vs multiple contracts issue, and whether MPS Housing had a real prospect of defeating the argument that there was a single contract. Looking at the parties’ intentions and their dealings, he considered that there was no real prospect of finding that there were multiple contracts. Accordingly, the adjudicator’s decision that the reference to adjudication was under a single contract was correct, and the decision was enforceable.
Commentary
While substance and jurisdiction were not found to be overlapping in this case, there may be instances where they are. As such, courts will need to consider the purpose for which it was necessary for an adjudicator to make a particular decision.
Clare Mendelle is a professional support lawyer and James Goldthorpe a paralegal at Sharpe Pritchard LLP
For further insight and resources on local government legal issues from Sharpe Pritchard, please visit the SharpeEdge page by clicking on the banner below.
This article is for general awareness only and does not constitute legal or professional advice. The law may have changed since this page was first published. If you would like further advice and assistance in relation to any issue raised in this article, please contact us by telephone or email
Click here to view our archived articles or search below.
|
ABOUT SHARPE PRITCHARD We are a national firm of public law specialists, serving local authorities, other public sector organisations and registered social landlords, as well as commercial clients and the third sector. Our team advises on a wide range of public law matters, spanning electoral law, procurement, construction, infrastructure, data protection and information law, planning and dispute resolution, to name a few key specialisms. All public sector organisations have a route to instruct us through the various frameworks we are appointed to. To find out more about our services, please click here. |
OUR RECENT ARTICLES
October 09, 2025
Twelve New Towns for the FutureJames Goldthorpe and Conrad Turnock summarise the New Towns Taskforce’s report to Government, published on 28th September, and ask - what next?
September 30, 2025
Key updates to the Administrative Court GuideChloe McQuillan and Jonathan Blunden dive into recent amendments to the Administrative Court Judicial Review Guide, exploring what they mean for practitioners.
September 12, 2025
Algorithm and State: Automated decision-making in the UK Public SectorBeatrice Wood explores the impact of Automated Decision making on the UK government and local authority sector.
September 12, 2025
The Nuclear Regulatory Taskforce Interim ReportBridget Newman discusses the report published by the Nuclear Regulatory Taskforce on the UK’s nuclear regulatory framework.
|
OUR KEY LOCAL GOVERNMENT CONTACTS |
||
Partner 020 7406 4600 Find out more |
||
Partner 020 7406 4600 Find out more |
||
Rachel Murray-Smith Partner 020 7406 4600 Find out more |