You Must Adjudicate First NEC3 imposes obligation to adjudicate first before commencing court proceedings.
Michael Comba discusses NEC3 imposing an obligation to adjudicate first before commencing court proceedings.
- Details
Greater Glasgow Health Board v Multiplex Construction Europe Ltd and others [2021] CSOH 115
The facts
The Greater Glasgow Health Board (the Employer) entered into a NEC3 ECC Option C contract (the Contract) with Multiplex (the Contractor) for the construction of a hospital. The Contract included the standard NEC optional dispute resolution clause, W2, which provides that a dispute will be referred to adjudication prior to being referred to the tribunal (in this case, the Scottish Courts). Referral to the tribunal can also only occur once a ‘notice of dissatisfaction’ has been served by a party dissatisfied by an adjudication’s outcome.
After the works had concluded several defects in the construction were discovered, and the Employer sought approximately £73m in damages from the Contractor. The Employer referred the matter immediately to the courts, arguing that the dispute was too complex for an adjudication. It claimed that the dispute, really concerning several individual disputes, would have required up to 22 individual adjudications. It argued that W2 impliedly excluded such complex disputes. The Contractor argued that adjudication had to occur first and that, in the absence of an adjudication, W2 served as a contractual bar on commencing court proceedings.
The judgment
The court held that complex disputes were not impliedly excluded from W2. It considered that it was foreseeable at the time of entering the Contract that such disputes may arise and so determined that, had the parties intended to exclude complex disputes, they would have done so explicitly. In any event, the court also held that the dispute was not intrinsically complex or unsuitable for adjudication, nor were 22 individual adjudications obviously required; that was a matter for the adjudicator to consider when the dispute was referred to adjudication.
The court, however, did not agree with the Contractor’s interpretation that W2 was a contractual bar. The obligation to first refer a dispute to adjudication could be waived by the parties and, while the court could not consider the merits of the claim in the absence of that waiver, the court’s jurisdiction was not fully ousted. This followed the reasoning of a recent similar case[1].
Analysis
Although a Scottish case, this judgment is nonetheless important for parties in England and Wales using the NEC form of contract and option W2. Disputing parties under contracts with this option must first refer the dispute to adjudication, regardless of size or value.
This case further underlines that, even for large and high-value claims, the courts continue to strongly support the use of adjudication as a means of dispute resolution ahead of using court proceedings. It is, therefore, crucial that employers and contractors fully acquaint themselves with their dispute resolution process as there is fair chance that they will have to refer to it sooner or later.
This article is for general awareness only and does not constitute legal or professional advice. The law may have changed since this page was first published. If you would like further advice and assistance in relation to any issue raised in this article, please contact us by telephone or email enquiries@sharpepritchard.co.uk.
[1] Fraserburgh Harbour Commissioners v McLaughlin & Harvey Ltd [2021] CSOH 8, 2021 S.L.T. 1009, [2021] 1 WLUK 281
Michael Comba is a Solicitor at Sharpe Pritchard LLP.
For further insight and resources on local government legal issues from Sharpe Pritchard, please visit the SharpeEdge page by clicking on the banner below.
This article is for general awareness only and does not constitute legal or professional advice. The law may have changed since this page was first published. If you would like further advice and assistance in relation to any issue raised in this article, please contact us by telephone or email enquiries@sharpepritchard.co.uk
Click here to view our archived articles or search below.
|
OUR RECENT ARTICLES IPA guidance 2025: Managing PFI distress and preparing for expiry
Jul 03, 2025
Aanya Gujral and David Owens dive into the recent guidance published on managing the risks associated with Private Finance Initiative (“PFI”) projects.
Data (Use and Access) Act – Updating Data Protection Law and more
Jul 03, 2025
On the 19th June 2025, the Data Use and Access Bill (“DUA Bill”) received Royal Assent to become the Data Use and Access Act 2025 (“DUA Act”).
Modifying subsidies: What is permitted and what is not?
Jun 24, 2025
Beatrice Wood and Oliver Slater explore recent developments and discuss the process of awarding subsidies.
Getting new PPP right: Smarter tools for smarter infrastructure
Jun 24, 2025
Nicola Sumner, Steve Gummer and Roseanne Serrelli discuss the 'dos and don'ts' of Public-private Partnerships in their new form.
Zones/RABs and heat networks: The path to an investible infrastructure asset class?
Jun 19, 2025
The UK’s new heat network zoning framework (the outlines for which were drawn by the Energy Act 2023) is set to redefine how low‑carbon heating is delivered by creating geographic zones, where district heat networks are the mandated, optimal solution.
Partial debt guarantees- Reviving Investment in UK Water Infrastructure
Jun 17, 2025
Is it Time for a Public Sector Major Infrastructure Debt Guarantor?
Court gives clarity on consultations : R (The National Council for Civil Liberties) and others v The Secretary of State for the Home Department
Jun 10, 2025
Chloe Woodward and Joe Walker discuss a recent judgment on when engagement with third parties constitute a formal consultation and must therefore adhere to case law on being 'run fairly'.
URS Corporation Limited v BDW Trading Limited [2025] UKSC 21 – Supreme Court hands down significant judgment for the construction industry
May 27, 2025
Helen Arthur explores a recent Supreme Court judgment on building safety in high-rise buildings, explaining what the decision means for defects claims.
Catch me if you can: Local government blazes a trail in increased SME spending
May 21, 2025
Juli Lau and Natasha Barlow take readers through the report published by the BCC on procurement spending.
Changing Course: Navigating Variations Under JCT and NEC Contracts
May 21, 2025
Tiah Weekes explains the process of changes to contracts in the field of construction.
Lessons in public consultation: High Court finds failures in local authority’s consideration of consultation responses
May 21, 2025
George McLellan and Samuel Hart explore the High Court decision ruling that Lambeth Council broke the law in the process of establishing an LTN in the borough.
Allocating risk in amended JCT contracts: Lessons from John Sisk & Son Limited v Capital & Centric (Rose) Limited
May 12, 2025
David Owens and Elizabeth Withers explore recent developments in construction contract case law.
|
ABOUT SHARPE PRITCHARD We are a national firm of public law specialists, serving local authorities, other public sector organisations and registered social landlords, as well as commercial clients and the third sector. Our team advises on a wide range of public law matters, spanning electoral law, procurement, construction, infrastructure, data protection and information law, planning and dispute resolution, to name a few key specialisms. All public sector organisations have a route to instruct us through the various frameworks we are appointed to. To find out more about our services, please click here. |
OUR NEXT EVENT
|
OTHER UPCOMING EVENTS
![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() |