The limits of an adjudicator's jurisdiction
Dr Paul Hughes and Anna Sidebottom look at the effect of Prater v Sisk [2021] on the ability of an Adjudicator to rely on previous 'out of jurisdiction' decisions between the same parties
- Details
The recently decided case of Prater v Sisk confirms that an Adjudicator’s decision is enforceable in circumstances where it is based (in part) on a previously decided decision, which the defendant alleges was made without jurisdiction. It also provides helpful commentary on the broad definition of dispute and interpretation of NEC3 Option W2 with regards to multiple adjudication referrals.
Background
The claimant (Prater) applied for summary judgment for the enforcement of an Adjudicator’s decision. The adjudication was commenced under Option W2 of the NEC3 Conditions of Subcontract, option A (2013).
The parties had entered a Subcontract for works to a new aircraft hangar at London Gatwick Airport. The Subcontract works were subject to delay and changes and resulted in a number of separate adjudications.
An earlier Adjudicator’s decision was of particular significance to the application. In that earlier adjudication Prater sought decisions in relation to: (a) the correct Subcontract Completion Date; (b) provisional sums within the Contract; and (c) Sisk’s entitlement to deductions for indirect losses.
In the present matter Prater sought payment which (in part) relied on the findings of that earlier adjudication. The Adjudicator awarded Prater a significant sum.
The parties’ respective cases
Sisk argued that the earlier decision was not binding as the referral did not relate to a single dispute but to three separate disputes and therefore that the Adjudicator did not have jurisdiction. Accordingly, Sisk submitted that the Adjudicator did not have jurisdiction in the present matter as it was partly based on the findings of an earlier adjudication.
Prater argued that the earlier adjudication was binding and enforceable as a matter of principle and contractual obligation unless challenged in the Court. Prater submitted that there were no valid grounds to challenge the Adjudicator’s jurisdiction because a challenge to an Adjudicator’s jurisdiction in an earlier referral did not constitute a valid challenge in a subsequent referral. Prater contended that the earlier adjudication stemmed from numerous issues arising out of a single disputed payment certificate and not multiple disputes.
Issues
The issues for the Court to decide were as follows:
Whether a lack of jurisdiction in relation to an earlier adjudication decision was capable of impugning the Adjudicator’s decision in a subsequent adjudication, where that subsequent decision was made (in part) on the findings of the earlier decision. If so, whether the Adjudicator did indeed lack jurisdiction in relation to that earlier decision.
Buehrlen J held that the Adjudicator’s decision was enforceable and should be upheld, finding that the Adjudicator had the relevant jurisdiction to make the decision whether or not an earlier decision upon which it relied was made without jurisdiction.
The principal points in that judgment can be summarised under the following headings:
Issue 1 – The Adjudicator’s jurisdiction in the subsequent adjudication
Buehrlen J agreed with Prater that “until an adjudication decision is challenged, either in arbitration or in court, it is binding on the parties”. Clause W2.3(11) of the Subcontract, under which the referral had been made, expressly stated that the Adjudicator’s decision is binding unless revised by the tribunal. Sisk had served a Notice of Dissatisfaction under WC2.4(2) of the Subcontract but had not taken any further steps to refer the earlier decision to the Court. The earlier decision was therefore binding on the parties and enforceable by Prater until successfully challenged by Sisk.
With regard to whether a decision that lacked the requisite jurisdiction made a subsequent adjudication a nullity, Buehrlen J found it did not. It fell to the aggrieved party (in this case, Sisk) to challenge the underlying decision, and unless and until it did that an adjudication decision would be binding on the parties and in any subsequent adjudications.
Issue 2 – Whether the Adjudicator lacked jurisdiction in the earlier adjudication
As to whether the Adjudicator lacked jurisdiction in relation to the earlier adjudication, the Buehrlen J found that the issues which were the subject of the earlier adjudication did not comprise multiple disputes.
The judgment clarified Akenhead J’s guidance in the Witney Town Council v Beam Construction (Cheltenham) Ltd [2011] EWHC 2332 (TCC) case as to what constitutes a single dispute. A dispute may comprise several distinct issues, which may be capable of being decided independently. A common sense approach should be used when determining the meaning of ‘dispute’. In this case, Buehrlen J found that the issues which were the subject of the earlier adjudication formed part of a larger dispute.
In reaching these conclusions, the Buehrlen J was obliged to take account of whether the Adjudicator had jurisdiction under NEC3 Option W2 to deal with more than one dispute in a single adjudication. Buehrlen J found that as a matter of contractual interpretation, there was no basis for the proposition that more than one dispute could be referred. The parties had not expressly agreed to more than one dispute being referred in a single adjudication and the drafting of NEC3 Option 2 certainly did not support that.
Comment
The case highlights the importance of promptly challenging an Adjudicator’s decision where a party contends that the Adjudicator lacked jurisdiction. Parties cannot use a subsequent adjudication enforcement hearing to open up and challenge an earlier Adjudicator’s decision.
Dr Paul Hughes is a senior associate and Anna Sidebottom a trainee solicitor at Sharpe Pritchard LLP.
For further insight and resources on local government legal issues from Sharpe Pritchard, please visit the SharpeEdge page by clicking on the banner below.
This article is for general awareness only and does not constitute legal or professional advice. The law may have changed since this page was first published. If you would like further advice and assistance in relation to any issue raised in this article, please contact us by telephone or email enquiries@sharpepritchard.co.uk
Click here to view our archived articles or search below.
|
OUR RECENT ARTICLES The CAT’s approach to Subsidy Decision Reviews: Fast, cheap and simple?
Jul 16, 2025
Olivia Dawson and Oliver Slater consider the Subsidy Control Act’s subsidy challenge regime, the Competition Appeal Tribunal’s (the “CAT’s”) approach to case management and costs, and what the future for challenges to subsidy decisions might look like.
Millbrook Healthcare Limited v Devon County Council – Its impact on local government procurement
Jul 16, 2025
Oliver Dickie, Christopher Watkins and George McLellan dive into the recent High Court judgment on interim relief in procurement claims.
Airport Subsidy Challenged in the CAT
Jul 09, 2025
Oliver Slater, Beatrice Wood and Steve Gummer dive into the latest Competition Appeal Tribunal subsidy control challenge, brought against the Welsh Government's subsidy to Cardiff Airport.
IPA guidance 2025: Managing PFI distress and preparing for expiry
Jul 03, 2025
Aanya Gujral and David Owens dive into the recent guidance published on managing the risks associated with Private Finance Initiative (“PFI”) projects.
Data (Use and Access) Act – Updating Data Protection Law and more
Jul 03, 2025
On the 19th June 2025, the Data Use and Access Bill (“DUA Bill”) received Royal Assent to become the Data Use and Access Act 2025 (“DUA Act”).
Modifying subsidies: What is permitted and what is not?
Jun 24, 2025
Beatrice Wood and Oliver Slater explore recent developments and discuss the process of awarding subsidies.
Getting new PPP right: Smarter tools for smarter infrastructure
Jun 24, 2025
Nicola Sumner, Steve Gummer and Roseanne Serrelli discuss the 'dos and don'ts' of Public-private Partnerships in their new form.
Zones/RABs and heat networks: The path to an investible infrastructure asset class?
Jun 19, 2025
The UK’s new heat network zoning framework (the outlines for which were drawn by the Energy Act 2023) is set to redefine how low‑carbon heating is delivered by creating geographic zones, where district heat networks are the mandated, optimal solution.
Partial debt guarantees- Reviving Investment in UK Water Infrastructure
Jun 17, 2025
Is it Time for a Public Sector Major Infrastructure Debt Guarantor?
Court gives clarity on consultations : R (The National Council for Civil Liberties) and others v The Secretary of State for the Home Department
Jun 10, 2025
Chloe Woodward and Joe Walker discuss a recent judgment on when engagement with third parties constitute a formal consultation and must therefore adhere to case law on being 'run fairly'.
URS Corporation Limited v BDW Trading Limited [2025] UKSC 21 – Supreme Court hands down significant judgment for the construction industry
May 27, 2025
Helen Arthur explores a recent Supreme Court judgment on building safety in high-rise buildings, explaining what the decision means for defects claims.
Catch me if you can: Local government blazes a trail in increased SME spending
May 21, 2025
Juli Lau and Natasha Barlow take readers through the report published by the BCC on procurement spending.
|
ABOUT SHARPE PRITCHARD We are a national firm of public law specialists, serving local authorities, other public sector organisations and registered social landlords, as well as commercial clients and the third sector. Our team advises on a wide range of public law matters, spanning electoral law, procurement, construction, infrastructure, data protection and information law, planning and dispute resolution, to name a few key specialisms. All public sector organisations have a route to instruct us through the various frameworks we are appointed to. To find out more about our services, please click here. |
OUR NEXT EVENT
|
OTHER UPCOMING EVENTS
![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() |